Four large and deep ptholes on Lynfield Park rd

Reported in the Potholes & road surface category anonymously at 13:19, Fri 27 December 2019

Sent to Bath and North East Somerset Council 1 minute later. Council ref: 1906453.

These potholes have been here for several months and they appear to be getting gradually bigger. In fact the whole road looks badly made. I have never seen so many large potholes in one road within a range of 20 feet of each other. I have to drive very slowly to try to avoid them.

Please can you do something about this as soon as possible.

Kind regards from Christian Liberati.

RSS feed of updates to this problem Receive email when updates are left on this problem.

Updates

  • Thank you for this report. We will review the details and carry out an inspection of the site if required.

    9 out of 10 Potholes & Road Surface reports are updated within 10 working days once we decide what action to take. To find out what we do and why it might take longer, please visit https://www.bathnes.gov.uk/ fmsroads

    If you have more information about the issue you can add an update to this report.

    Let us know what you think about this update: http://bit.ly/ 2O2xQVt

    Posted by Bath and North East Somerset Council at 13:20, Fri 27 December 2019

  • Large potholes across most of the road ideally will need resurfacing but if xan bw patched in the mean time before and accident happens

    Posted anonymously at 17:16, Sat 28 December 2019

  • We've looked into this report and passed the details on to our contractor. They will plan and carry out any work needed. 4 out of 5 issues are updated within 30 working days.

    To find out what we do and why it might take longer, please visit https://www.bathnes.gov.uk/ fmsroads01

    We'll update this report when the contractor has completed their work.

    Let us know what you think about this update: http://bit.ly/ 2O2xQVt

    State changed to: Action scheduled

    Posted by Bath and North East Somerset Council at 14:45, Mon 30 December 2019

  • Some potholes have been filled on this road but there is still one very large at the side of the road about half way down the road

    Posted anonymously at 19:08, Thu 4 June 2020

  • We have now closed this report. If you disagree with this decision, please raise a new report. Please include your previous reference number and an explanation of why you wish the report to be reopened.

    State changed to: Closed

    Posted by Systems Team at 10:33, Friday 13 January 2023

This report is now closed to updates. You can make a new report in the same location.