You can move around with your keyboard
plus
minus
left
right
Drop pin on the map to start a new report
space
Press space again to adjust the location
space
Back to all reports

Drain blocked and broken road

Reported via Android in the Flooding of a road or pavement category anonymously at 10:45, Sat 29 February 2020

Sent to Bath and North East Somerset Council 7 minutes later. Council ref: 2017523.

Here is the drain which is always blocked causing surface flooding and now damaged road each time it rains more flooding and more damage to road .

RSS feed of updates to this problem Receive email when updates are left on this problem.

Updates

  • Thank you for this report. We will review the details and carry out an inspection of the site if required.

    4 out of 5 Road or Pavement Flooding reports are updated within 7 working days once we decide what action to take. To find out what we do and why it might take longer, please visit https://www.bathnes.gov.uk/ fmsroads09

    If you have more information about the issue you can add an update to this report.

    State changed to: In progress

    Posted by Bath and North East Somerset Council at 10:52, Sat 29 February 2020

  • We've looked into this report and passed the details on to our contractor. They will plan and carry out any work needed. 4 out of 5 issues are updated within 23 working days.

    To find out what we do and why it might take longer, please visit https://www.bathnes.gov.uk/ fmsroads10

    We'll update this report when the contractor has completed their work.

    State changed to: Action scheduled

    Posted by Bath and North East Somerset Council at 10:37, Thu 5 March 2020

  • Here is photos taken this morning (5/03/2020)that clearly shows the situation after rain

    Posted anonymously at 11:42, Thu 5 March 2020

  • Questionnaire filled in by problem reporter

    State changed to: Fixed

    Posted anonymously at 11:21, Sat 28 March 2020

  • We've looked into this report and passed the details on to our contractor. They will plan and carry out any work needed. 4 out of 5 issues are updated within 23 working days.

    To find out what we do and why it might take longer, please visit https://www.bathnes.gov.uk/ fmsroads10

    We'll update this report when the contractor has completed their work.

    State changed to: Action scheduled

    Posted by Systems Team at 10:38, Tue 28 September 2021

This report is now closed to updates. You can make a new report in the same location.