Fixed
Road subsidence adjacent to gully
Reported via desktop in the Potholes & road surface category anonymously at 12:17, Thu 18 November 2021
Sent to Bath and North East Somerset Council less than a minute later. Council ref: 3130837.
This has been reported several times in the past year and most recently this June. The gully has now been cleared but the depression in the tarmac remains, bypassing the gully and rendering it ineffective.
Updates
-
Thank you for this report. We will review the details and carry out an inspection of the site if required.
9 out of 10 Potholes & Road Surface reports are updated within 10 working days once we decide what action to take. To find out what we do and why it might take longer, please visit https://www.bathnes.gov.uk/ fmsroads
If you have more information about the issue you can add an update to this report.
State changed to: In progress
Posted by Systems Team at 12:18, Thu 18 November 2021
-
We've looked into this report and passed the details on to our contractor. They will plan and carry out any work needed. 4 out of 5 issues are updated within 30 working days.
To find out what we do and why it might take longer, please visit https://www.bathnes.gov.uk/ fmsroads01
We'll update this report when the contractor has completed their work.
State changed to: Action scheduled
Posted by Systems Team at 10:35, Mon 22 November 2021
-
Reported several times this year
Posted anonymously at 13:05, Thu 16 December 2021
Still open, via questionnaire -
Our contractor has now completed their work. If this issue reoccurs please log a new report.
Thank you for using Fix My Street. Reporting issues like this online can help us deal with them more efficiently.
To find out more about what we do, please visit https://www.bathnes.gov.uk/ fmsroads04
State changed to: Fixed
Posted by Systems Team at 12:07, Tue 11 January 2022
This report is now closed to updates from the public. You can make a new report in the same location.