report here Reposition
report here
Fixed
Do it again!
Reported via iOS in the Potholes & road surface category by Clive Dixon at 21:12, Saturday 1 April 2023
Sent to Bath and North East Somerset Council less than a minute later. Council ref: 4387197.
It’s on the junction between Queens Road and Caernarfon Road. This was filled in a few months ago as you can see from the photograph. It wasn’t done properly and needs doing again as this pothole is on a junction and dangerous, not only to cars but especially to 2 wheeled vehicles like motorcycles and cycles. The whole of the section between this junction and the Queens Road shops is very, very poorly maintained and has numerous potholes. Also the material from the potholes is all over the road creating yet another danger. They too need sorting out as soon as possible before an accident occurs.
Updates
-
Thank you for your report. We will review the details you submitted and will inspect the site if necessary.
We respond to 9 out of 10 reports of potholes and road surface issues within 10 working days, once we have decided on the best course of action. You can visit our website to find out what we do and why in some cases it can take longer than you might expect. https://beta.bathnes.gov.uk/ how-we-deal-problems-road-networkYou can support our investigation by providing as much detail as possible. If you can provide any extra information, please add an update to this report.
State changed to: In progress
Posted by Systems Team at 21:12, Saturday 1 April 2023
-
Thank you for your report. We have investigated your issue and have passed the details onto our contractor. They will plan and complete any necessary work. We will update your report when the contractor has completed the work. We respond to 4 out of 5 reports within 30 working days, once we have decided on the best course of action.
You can visit our website to find out what we do and why it can take longer than you might expect. https://beta.bathnes.gov.uk/ how-we-deal-problems-road-network
State changed to: Action scheduled
Posted by Systems Team at 08:34, Tuesday 4 April 2023
-
Our contractor has now completed their work. If this issue reoccurs please log a new report.
Thank you for using Fix My Street. Reporting issues like this online can help us deal with them more efficiently.
To find out more about what we do, please visit https://www.bathnes.gov.uk/ fmsroads04
State changed to: Fixed
Posted by Systems Team at 13:07, Thursday 6 April 2023
This report is now closed to updates. You can make a new report in the same location.