Potholes along edge of road
Reported via desktop in the Potholes & road surface category anonymously at 08:56, Wednesday 5 April 2023
Sent to Bath and North East Somerset Council less than a minute later. Council ref: 4400252.
There are several potholes along the edge of the road (uphill side) in in the 50 metres section downhill from the National Trust sign. These force cyclists out into the path of passing cars.
Updates
-
Thank you for your report. We will review the details you submitted and will inspect the site if necessary.
We respond to 9 out of 10 reports of potholes and road surface issues within 10 working days, once we have decided on the best course of action. You can visit our website to find out what we do and why in some cases it can take longer than you might expect. https://beta.bathnes.gov.uk/ how-we-deal-problems-road-networkYou can support our investigation by providing as much detail as possible. If you can provide any extra information, please add an update to this report.
State changed to: In progress
Posted by Systems Team at 08:57, Wednesday 5 April 2023
-
Thank you for your report. We have investigated your issue and have passed the details onto our contractor. They will plan and complete any necessary work. We will update your report when the contractor has completed the work. We respond to 4 out of 5 reports within 30 working days, once we have decided on the best course of action.
You can visit our website to find out what we do and why it can take longer than you might expect. https://beta.bathnes.gov.uk/ how-we-deal-problems-road-network
State changed to: Action scheduled
Posted by Systems Team at 12:03, Friday 21 April 2023
-
Still open, via questionnaire, 09:08, Wednesday 3 May 2023
-
Still open, via questionnaire, 10:14, Wednesday 31 May 2023
-
This section of North Road, between King Edwards School and Quarry Road into the University is full of potholes and bad repairs. It was most recently patched in August 2023 and has only made it worse, with large lumps of new surface on top of old uneven patches. And the repair team have ignored several large, long potholes yet patched others right next to them. The whole section needs a full survey and repair, not just small patches.
Posted anonymously at 16:55, Thursday 14 September 2023
-
‘We’ve recently performed a cleansing exercise in our system to close down all outstanding jobs that were completed some time ago. This closure is for reference only and you do not need to do anything’.
State changed to: Fixed
Posted by Systems Team at 09:19, Thursday 7 December 2023
Moderated by Bath and North East Somerset Council at 09:26, Thursday 7 December 2023
This report is now closed to updates. You can make a new report in the same location.