There is water erroding the road at the bottom of our drive

Reported via mobile in the Flooding of a road or pavement category anonymously at 11:00, Fri 18 August 2023

Sent to Bath and North East Somerset Council less than a minute later. Council ref: 4904299.

Water has been rising by the road edge here since last year. Wessex Water claim that they have tested it and they believe it is natural spring water. It has erroded the road surface to the degree that a growing pothole has appeared and I'm concerned that the road surface may be dropping. Please note that Wessex Water has been carrying a lot of work in the area around our house over the last couple of years and this seemed to start not long after they were working in the road.

RSS feed of updates to this problem Receive email when updates are left on this problem.

Updates

  • Thank you for your report. We will review the details you submitted and will inspect the site if necessary.

    You can support our investigation by providing as much detail as possible. If you can provide any extra information, please add an update to this report.

    We respond to 4 out of 5 reports of road or pavement flooding within 7 working days, once we have decided on the best course of action. You can visit our website to find out what we do and why it can take longer than you might expect.https://beta.bathnes.gov.uk/ how-we-deal-problems-road-network

    State changed to: In progress

    Posted by Systems Team at 11:00, Fri 18 August 2023

  • Thank you for your report. We have investigated your issue and have passed the details onto our contractor. They will plan and complete any necessary work.

    We will update your report when the contractor has completed the work. We respond to 4 out of 5 reports within 23 working days, once we have decided on the best course of action. You can visit our website to find out what we do and why it can take longer than you might expect. https://beta.bathnes.gov.uk/ how-we-deal-problems-road-network

    State changed to: Action scheduled

    Posted by Systems Team at 13:52, Fri 18 August 2023

  • We are pleased to say that our contractor has now completed their work. If this issue reoccurs, please log a new report. You can visit our website to find out more about what we do. Thank you for using Fix My Street, your online reporting helps us deal with problems more efficiently, while keeping you informed.https://beta.bathnes.gov.uk/ how-we-deal-problems-road-network

    State changed to: Fixed

    Posted by Systems Team at 15:26, Fri 22 September 2023

This report is now closed to updates from the public. You can make a new report in the same location.