Birdcage walk path
Reported via mobile in the Pavement damage category anonymously at 16:05, Wed 13 September 2023
Sent to Bath and North East Somerset Council less than a minute later. Council ref: 4990861.
Birdcage walk path is uneven, cracking and dangerous under foot - lots of trip hazards. Kids use this path daily for school and the elderly use it for quick access back to bungalows.
Updates
-
Thank you for your report. We will review the details you submitted and will inspect the site if necessary. You can support our investigation by providing as much detail as possible. If you can provide any extra information, please add an update to this report.
We respond to 9 out of 10 reports within 10 working days, once we have decided on the best course of action. You can visit our website to find out what we do and why it can take longer than you might expect. https://beta.bathnes.gov.uk/ how-we-deal-problems-road-network
State changed to: In progress
Posted by Systems Team at 16:05, Wed 13 September 2023
-
Thank you for your report. We have investigated your issue and have passed the details onto our contractor. They will plan and complete any necessary work. We will update your report when the contractor has completed the work. We respond to 4 out of 5 reports within 30 working days, once we have decided on the best course of action.
You can visit our website to find out what we do and why it can take longer than you might expect. https://beta.bathnes.gov.uk/ how-we-deal-problems-road-network
State changed to: Action scheduled
Posted by Systems Team at 10:54, Thu 14 September 2023
-
Not fixed. And really dangerous under foot.
Posted anonymously at 16:39, Wed 11 October 2023
Still open, via questionnaire -
Still not fixed
Posted anonymously at 20:07, Wed 8 November 2023
Still open, via questionnaire -
We are pleased to say that our contractor has now completed their work. If this issue reoccurs, please log a new report. You can visit our website to find out more about what we do. Thank you for using Fix My Street, your online reporting helps us deal with problems more efficiently, while keeping you informed.https://beta.bathnes.gov.uk/ how-we-deal-problems-road-network
State changed to: Fixed
Posted by Systems Team at 09:42, Tue 5 December 2023
-
A few cracks have been filled but the biggest issue with the path lifting and cracking hasn't been rectified, there's a huge bump!
State changed to: Open
Posted anonymously at 21:08, Wed 6 December 2023
Still open, via questionnaire -
Cracks filled but path all uneven due to tree / bush roots
Posted anonymously at 21:54, Wednesday 3 January 2024
Still open, via questionnaire
Provide an update