White lines need repainting

Reported via mobile in the Faded road markings category anonymously at 20:16, Mon 2 October 2023

Sent to Bath and North East Somerset Council less than a minute later. Council ref: 5054654.

The white lines are faded and due to the new parking zones we have an influx (especially around school drop times) of cars. I have raised this but was told it was basically not an issue. I would like this re examined please. The above photo was taken this morning. Nothing bigger than a car could fit through this space and this is happening constantly. My whole road didn't have the bins collected last week due to the fact they couldn't get the van through. I worry ambulances won't be able to get through to the old people's home. Thank you.

RSS feed of updates to this problem Receive email when updates are left on this problem.

Updates

  • Thank you for your report. We will review the details you submitted and will inspect the site if necessary.

    You can support our investigation by providing as much detail as possible. If you can provide any extra information, please add an update to this report. We will update your report as soon as we have decided on the best course of action.

    You can visit our website to find out what we do and why it can take longer than you might expect. https://beta.bathnes.gov.uk/ how-we-deal-problems-road-network

    State changed to: In progress

    Posted by Systems Team at 20:16, Mon 2 October 2023

  • We are pleased to say that we have now resolved your issue. If this issue reoccurs, please log a new report. You can visit our website to find out more about what we do. Thank you for using Fix My Street, your online reporting helps us deal with problems more efficiently, while keeping you informed. https://beta.bathnes.gov.uk/ how-we-deal-problems-road-network

    State changed to: Fixed

    Posted by Systems Team at 14:39, Mon 9 October 2023

  • Thank you for your report. We will review the details you submitted and will inspect the site if necessary.

    You can support our investigation by providing as much detail as possible. If you can provide any extra information, please add an update to this report. We will update your report as soon as we have decided on the best course of action.

    You can visit our website to find out what we do and why it can take longer than you might expect. https://beta.bathnes.gov.uk/ how-we-deal-problems-road-network

    State changed to: In progress

    Posted by Systems Team at 09:58, Tue 10 October 2023

  • We've looked into this report and are investigating the issue.
    We will update this report once we decide what action to take.

    State changed to: Investigating

    Posted by Systems Team at 15:22, Thu 12 October 2023

  • Thank you for your enquiry.

    This has been passed to our liveable Neighbourhoods team to investigate

    State changed to: Internal referral

    Posted by Bath and North East Somerset Council at 15:29, Thu 12 October 2023

  • Thank you for your report. We will review the details you submitted and will inspect the site if necessary.

    You can support our investigation by providing as much detail as possible. If you can provide any extra information, please add an update to this report. We will update your report as soon as we have decided on the best course of action.

    You can visit our website to find out what we do and why it can take longer than you might expect. https://beta.bathnes.gov.uk/ how-we-deal-problems-road-network

    State changed to: In progress

    Posted by Systems Team at 16:35, Tue 17 October 2023

  • Thank you for your report. We have investigated your issue and have passed the details onto our contractor.

    They will plan and complete any necessary work. We will update your report when the contractor has completed the work. You can visit our website to find out what we do and why it can take longer than you might expect. https://beta.bathnes.gov.uk/ how-we-deal-problems-road-network

    State changed to: Action scheduled

    Posted by Systems Team at 13:52, Tue 24 October 2023

  • We are pleased to say that our contractor has now completed their work. If this issue reoccurs, please log a new report. You can visit our website to find out more about what we do. Thank you for using Fix My Street, your online reporting helps us deal with problems more efficiently, while keeping you informed.https://beta.bathnes.gov.uk/ how-we-deal-problems-road-network

    State changed to: Fixed

    Posted by Systems Team at 10:57, Mon 11 December 2023

This report is now closed to updates from the public. You can make a new report in the same location.