Flooding outside of cemetery

Reported via desktop in the Flooding of a road or pavement category anonymously at 11:53, Monday 25 November 2024

Sent to Bath and North East Somerset Council less than a minute later. Council ref: 6780962.

The road outside the cemetery is flooded due to heavy rain and water level yet again. There is no drain in this location on the road. This is causing issues with traffic driving on the wrong side of the road , which could result in an accident. Subsequently the water is being dispersed into the cemetery, especially if vehicles are travelling at the speed limit but not slowly down due to the hazard. This is an on going problem when there is heavy rain and causes issues within the cemetery where we have installed soakaways and drainage to mitigate as much flooding as possible. This is also causing distress to the bereaved families and visitors to the cemetery.

RSS feed of updates to this problem Receive email when updates are left on this problem.

Updates

  • Thank you for your report. We will review the details you submitted and will inspect the site if necessary.

    You can support our investigation by providing as much detail as possible. If you can provide any extra information, please add an update to this report.

    We respond to 4 out of 5 reports of road or pavement flooding within 7 working days, once we have decided on the best course of action. You can visit our website to find out what we do and why it can take longer than you might expect.https://beta.bathnes.gov.uk/ how-we-deal-problems-road-network

    State changed to: In progress

    Posted by Systems Team at 11:53, Monday 25 November 2024

  • Thank you for your report. We have investigated your issue and have passed the details onto our contractor. They will plan and complete any necessary work.

    We will update your report when the contractor has completed the work. We respond to 4 out of 5 reports within 23 working days, once we have decided on the best course of action. You can visit our website to find out what we do and why it can take longer than you might expect. https://beta.bathnes.gov.uk/ how-we-deal-problems-road-network

    State changed to: Action scheduled

    Posted by Systems Team at 10:34, Friday 29 November 2024

  • We are pleased to say that our contractor has now completed their work. If this issue reoccurs, please log a new report. You can visit our website to find out more about what we do. Thank you for using Fix My Street, your online reporting helps us deal with problems more efficiently, while keeping you informed.https://beta.bathnes.gov.uk/ how-we-deal-problems-road-network

    State changed to: Fixed

    Posted by Systems Team at 10:10, Thursday