Action scheduled
Between 58--66 leighton road
Reported via mobile in the Potholes & road surface category anonymously at 16:30, Monday 8 June 2026
Sent to Bath and North East Somerset Council less than a minute later. Council ref: 9582765.
Firstly the numerous potholes have been evident for months and are becoming worse. AND the whole road surface has broken up and again road is covered with gravel which sprays all over potentially damaging cars and injuring pedestrians. This has been reported many times but no permanent repair has been completed..
Updates
-
Thank you for your report. We will review the details you submitted and will inspect the site if necessary.
We respond to 9 out of 10 reports of potholes and road surface issues within 10 working days, once we have decided on the best course of action. You can visit our website to find out what we do and why in some cases it can take longer than you might expect. https://beta.bathnes.gov.uk/ how-we-deal-problems-road-networkYou can support our investigation by providing as much detail as possible. If you can provide any extra information, please add an update to this report.
State changed to: In progress
Posted by Systems Team at 16:31, Monday 8 June 2026
-
We have looked at this issue and included it in an existing programme of work.
The report is now closed, further comments may not be monitored.State changed to: Internal referral
Posted by Systems Team at 13:22, Wednesday 10 June 2026
-
Thank you for your report. We have investigated your issue and have passed the details onto our contractor. They will plan and complete any necessary work. We will update your report when the contractor has completed the work. We respond to 4 out of 5 reports within 30 working days, once we have decided on the best course of action.
You can visit our website to find out what we do and why it can take longer than you might expect. https://beta.bathnes.gov.uk/ how-we-deal-problems-road-network
State changed to: Action scheduled
Posted by Systems Team at 13:22, Wednesday 10 June 2026
-
Various pot hole repairs were marked out about a month ago between postal 46 to 70, Leighton Road. Two only of the many repairs were carried out very promptly but the remainder are untouched. Please can you advise when these will be dealt with?
Posted anonymously at 10:36, Thursday 9 July 2026
Provide an update
Your information will only be used in accordance with our privacy policy